Parallel mutation testing is realized in dextool mutate by using the same database in multiple instances via a symlink to a master database. Each instance of dextool have their own source tree and build environment but the database that is used is one and the same because of the symlink. This approach scales reasonably well up to five parallel instances.

Lets say you want to setup parallel execution of googletest with two instances. First clone the source code to two different locations.

git clone https://github.com/google/googletest.git gtest1
git clone https://github.com/google/googletest.git gtest2

Configure each instance appropriately. As if they would run the mutation testing by them self. When you are done it should look something like this.

ls -a gtest1
build/ ..... .dextool_mutate.toml test.sh build.sh
ls -a gtest2
build/ ..... .dextool_mutate.toml test.sh build.sh

The next step is the analyze. This is only executed in one of the instances. Lets say gtest1.

cd gtest1
dextool mutate analyze

Now comes the magic that makes it parallel. Create a symlink in gtest2 to the database in gtest1.

cd gtest2
ln -s ../gtest1/dextool_mutate.sqlite3

Everything is now prepared for the parallel test phase. Start an instance of dextool mutate in each of the directories.

cd gtest1
dextool mutate test
# new console
cd gtest2
dextool mutate test

Done! This can significantly cut down on the test time.

You will now and then see output in the console about the database being locked. That is as it should be. As noted earlier in this guide it scales OK to five instances. This is the source of the scaling problem. The more instances the more lock contention for the database.